Could Any one suggest me the equipment i need please.

With a quarter cabinet, you'd need to supply the following:

PDU

Switch

Power cables & network cables for your equipment

Comments

  • Umm, that's about it apart from labelling the server. (I can't remember of any other things I had to mail in when I colo'd)

  • because that's my first time to colo..and i don't know which band is good

  • @ttbbs168: It depends on whether you are going to rack this yourself or have the colo provider do it for you. But:

    1. Screws + retained nuts - check gauge of rack

    2. PDU should be provided on 1/4 rack, if not then make sure you get confirmation of the power feed connector type. Best to get a switched PDU so you can remote reboot without having to pay for remote hands to do it.

    3. Switch

    4. Power / Ethernet / KVM

    5. Rails for the servers (also check that the depth of the rack is sufficient for the server)

    6. Is it 2 post or 4 post rack? You may need to get specific rails for the equipment

  • letboxletbox Member, Patron Provider
    edited August 2015

    all that good as @MarkTurner mentioned. If you can't use rails try Gruber. Ask the provider some people won't require rails.

  • PhotonVPSPhotonVPS Member, Host Rep

    Pretty sure the providers includes the PDU in a 1/4 setup.

  • ClouviderClouvider Member, Patron Provider

    @PhotonVPS said:
    Pretty sure the providers includes the PDU in a 1/4 setup.

    You can't generalise. Depends on the contract / offer.

  • jbilohjbiloh Administrator, Veteran

    Everyone is going to be different. For the most part we include PDUs in 1/4 cabinet deals. At the same time we shy away from them and prefer to start with 1/2 cabinets.

  • @MarkTurner said:
    ttbbs168: It depends on whether you are going to rack this yourself or have the colo provider do it for you. But:

    1. Screws + retained nuts - check gauge of rack

    2. PDU should be provided on 1/4 rack, if not then make sure you get confirmation of the power feed connector type. Best to get a switched PDU so you can remote reboot without having to pay for remote hands to do it.

    3. Switch

    4. Power / Ethernet / KVM

    5. Rails for the servers (also check that the depth of the rack is sufficient for the server)

    6. Is it 2 post or 4 post rack? You may need to get specific rails for the equipment

    Again, it depends whether the provider lends you that equipment during the period of which you colocate with them :)

  • I need to know the band that people use. thanks .

  • dustincdustinc Member, Patron Provider, Top Host

    @ttbbs168 said:
    I need to know the band that people use. thanks .

    I believe you mean brand? If so, PDUMH20 is a decent PDU, Rackmountbale, and 1U (perfect for 1/4 racks)

  • doghouchdoghouch Member
    edited August 2015

    @dustinc I didn't have enough time to visit the QN Datacenter in LA... aw :/


    I really wanted to see the operations, but to @ttbbs168: collocating with QN would be a good choice as they are just plain awesome. Good network, nice facilities, everything I could dream of.

Sign In or Register to comment.